Grain storage hall and site infrastructure
Back to references Sudár Agro Kft.

2 230 m²
grain storage floor area
3 650 m²
concrete paving
420 million HUF
investment value
1 pcs
firefighting water tank
1 pcs
stormwater drainage system
Grant-funded
Grant-funded

Starting point

At Sudár Agro Kft.’s site in Mezőcsokonya, storage capacity fell short at harvest time, so the farm planned to build a new grain storage hall with grant funding. Besides the store itself, on-site traffic, fire protection and stormwater drainage also had to be provided for.

Client Sudár Agro Kft.
Location Mezőcsokonya, Somogy County
Category Agriculture
Year of handover 2023
Financing Funded by tender
Our services

Challenges

The project involved several tasks that had to be coordinated and completed by the agreed deadline:

  • construction of a 2 230 m² grain storage hall;
  • 3 650 m² of heavy-duty concrete paving on transport routes and turning areas;
  • a firefighting water tank in line with fire safety regulations;
  • stormwater drainage to protect the site.

We were also tasked with optimising the permit drawings to reduce construction costs. In addition, the documentation required for the grant settlement had to be kept in order while construction was still under way.


Solution

We managed the entire construction of the site as general contractor. We were not involved in the preparation phase, but we optimised the permit drawings we received, which reduced construction costs.

The concrete paving and structural work were carried out with our own machinery and our own specialists, so we kept the schedule under control throughout. We also handled the grant settlement from start to finish. From the first meeting to the occupancy permit, the client had a single responsible partner.


Project images


Results and impact

The project was completed in 7 months, by the agreed deadline. The farm gained new storage capacity, together with the associated concrete paving, firefighting water tank and stormwater drainage.

The grant settlement was successfully closed and the farmer received the grant funding.

2 230 m²
grain storage floor area
420 million HUF
investment value
7 months
construction time
Handed over on schedule
Handed over on schedule
Grant claim settled
Grant claim settled

Years later:

We handed the site over in 2023, and it has been in continuous operation ever since.

Do you have a plan or just an idea? Let’s talk about it!

Thinking about a similar investment?

Get in touch with us and we will help you realize your ideas – from foundation to completion, all in one hand on solid ground. The consultation is without obligation.

Or call us: +36 82 577 440
Our references

Our previous works